— Project Summary

Queue ID
SOCO-IC-1122
Capacity
79.9 MW
Technology
Solar
Status
active
Location
Montgomery, AL
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarSOCOLBNL

79.9 MW generation in Montgomery, AL · In queue since March 2023 · Proposed COD September 2027

79.9 MW

Capacity

1

Components

Solar

3 years

In Queue

Suspended

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 6m

In Study38%
Queue EntryMar 1, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-09-30

Project Details

State

AL

County

Montgomery

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Pike County - Snowdoun 230 kV Line

Data Source

LBNL

No news available for this project.