BetaActiveBatterySOCOLBNL
100 MW storage in Carroll, GA · In queue since January 2023 · Proposed COD August 2027
100 MW
Capacity
1
Components
Battery
3y 2m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 7m
Construction75%
Queue EntryJan 31, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2027-08-15
Project Details
State
GA
County
Carroll
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Roopville DS Substation 230 kV Bus
Data Source
LBNL
No news available for this project.