— Project Summary

Queue ID
SOCO-IC-1114
Capacity
951 MW
Technology
Gas
Status
active
Location
Autauga, AL
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveGasSOCOLBNL

951 MW generation in Autauga, AL · In queue since January 2023 · Proposed COD July 2024

951 MW

Capacity

1

Components

Gas

3y 2m

In Queue

IA Executed

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

1y 6m

Schedule

21 months past proposed COD

Construction75%
Queue EntryJan 10, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2024-07-01

Project Details

State

AL

County

Autauga

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Billingsley SS Substation 500 kV Bus

Data Source

LBNL