BetaActiveSolarSOCOLBNL
200 MW generation in Lamar, MS · In queue since January 2023 · Proposed COD November 2027
200 MW
Capacity
1
Components
Solar
3y 2m
In Queue
Suspended
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 10m
In Study38%
Queue EntryJan 9, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-11-01
Project Details
State
MS
County
Lamar
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Hattiesburg Southwest - Adams Creek 230 kV LIne
Data Source
LBNL
No news available for this project.