225 MW generation in Taylor, GA · In queue since November 2022 · Proposed COD June 2027
225 MW
Capacity
1
Components
Solar
3y 4m
In Queue
Suspended
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 7m
In Study38%
Queue EntryNov 25, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-15
Project Details
State
GA
County
Taylor
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Butler DS Substation 230 kV Bus
Data Source
LBNL
No news available for this project.