200 MW generation in Emanuel, GA · In queue since November 2022 · Proposed COD June 2026
200 MW
Capacity
1
Components
Solar
3y 4m
In Queue
Suspended
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 7m
In Study38%
Queue EntryNov 25, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-15
Project Details
State
GA
County
Emanuel
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Vidalia - Wadley Primary (Black) 230 kV Line
Data Source
LBNL
No news available for this project.