— Project Summary

Queue ID
SOCO-IC-1094
Capacity
200 MW
Technology
Solar
Status
active
Location
Irwin, GA
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarSOCOLBNL

200 MW generation in Irwin, GA · In queue since November 2022 · Proposed COD June 2026

200 MW

Capacity

1

Components

Solar

3y 4m

In Queue

Suspended

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 7m

In Study38%
Queue EntryNov 22, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-15

Project Details

State

GA

County

Irwin

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

North Tifton - Stump Creek 230 kV Line

Data Source

LBNL