— Project Summary

Queue ID
SOCO-IC-1091
Capacity
300 MW
Technology
Battery
Status
active
Location
Mobile, AL
Region
Southeast
Developer
IA Status
Suspended

BetaActiveBatterySOCOLBNL

300 MW storage in Mobile, AL · In queue since November 2022 · Proposed COD March 2027

300 MW

Capacity

1

Components

Battery

3y 4m

In Queue

Suspended

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 4m

In Study38%
Queue EntryNov 17, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-03-31

Project Details

State

AL

County

Mobile

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Big Creek - Chickasaw 230 kV Line

Data Source

LBNL

No news available for this project.