300 MW storage in Mobile, AL · In queue since November 2022 · Proposed COD March 2027
300 MW
Capacity
1
Components
Battery
3y 4m
In Queue
Suspended
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 4m
In Study38%
Queue EntryNov 17, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-03-31
Project Details
State
AL
County
Mobile
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Big Creek - Chickasaw 230 kV Line
Data Source
LBNL