BetaActiveSolarSOCOLBNL
125 MW generation in Perry, MS · In queue since November 2022 · Proposed COD July 2027
125 MW
Capacity
1
Components
Solar
3y 4m
In Queue
Suspended
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 8m
In Study38%
Queue EntryNov 9, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-07-01
Project Details
State
MS
County
Perry
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Eaton - Lucedale 115 kV Line
Data Source
LBNL