— Project Summary

Queue ID
SOCO-IC-1089
Capacity
125 MW
Technology
Solar
Status
active
Location
Perry, MS
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarSOCOLBNL

125 MW generation in Perry, MS · In queue since November 2022 · Proposed COD July 2027

125 MW

Capacity

1

Components

Solar

3y 4m

In Queue

Suspended

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 8m

In Study38%
Queue EntryNov 9, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-07-01

Project Details

State

MS

County

Perry

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Eaton - Lucedale 115 kV Line

Data Source

LBNL

No news available for this project.