200 MW generation in Lee, GA · In queue since November 2022 · Proposed COD June 2027
200 MW
Capacity
1
Components
Solar
3y 4m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 7m
Construction75%
Queue EntryNov 7, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
GA
County
Lee
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
North Americus - Palmyra 230 kV Line
Data Source
LBNL