— Project Summary

Queue ID
SOCO-IC-1086
Capacity
160 MW
Technology
Solar+Battery
Status
active
Location
Perry, AL
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarBatterySOCOLBNL

160 MW hybrid in Perry, AL · In queue since November 2022 · Proposed COD July 2026

160 MW

Capacity

2

Components

Solar + Battery

3y 4m

In Queue

Suspended

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 8m

In Study38%
Queue EntryNov 2, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-07-15

Technology
Solar80 MW · 50%
Battery80 MW · 50%
Project Details

State

AL

County

Perry

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Greene County - North Selma 230 kV Line

Data Source

LBNL