BetaActiveSolarBatterySOCOLBNL
160 MW hybrid in Perry, AL · In queue since November 2022 · Proposed COD July 2026
160 MW
Capacity
2
Components
Solar + Battery
3y 4m
In Queue
Suspended
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 8m
In Study38%
Queue EntryNov 2, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-07-15
Technology
Solar80 MW · 50%
Battery80 MW · 50%
Project Details
State
AL
County
Perry
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Greene County - North Selma 230 kV Line
Data Source
LBNL
No news available for this project.