BetaActiveSolarSOCOLBNL
470 MW generation in Coweta, GA · In queue since October 2022 · Proposed COD August 2027
470 MW
Capacity
1
Components
Solar
3y 5m
In Queue
Suspended
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 10m
In Study38%
Queue EntryOct 26, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-08-09
Project Details
State
GA
County
Coweta
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Plant Wansley Substation 500 kV Bus
Data Source
LBNL
No news available for this project.