BetaActiveSolarSOCOLBNL
80 MW generation in Montgomery, AL · In queue since October 2022 · Proposed COD December 2026
80 MW
Capacity
1
Components
Solar
3y 5m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 2m
Construction75%
Queue EntryOct 11, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-12-16
Project Details
State
AL
County
Montgomery
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Montgomery SS - Snowdoun 230 kV Line
Data Source
LBNL