80 MW generation in Dallas, AL · In queue since October 2022 · Proposed COD July 2027
80 MW
Capacity
1
Components
Solar
3y 5m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 9m
Construction75%
Queue EntryOct 5, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-07-15
Project Details
State
AL
County
Dallas
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Millers Ferry Dam (COE) - Selma 115 kV Line
Data Source
LBNL