BetaActiveSolarSOCOLBNL
110.5 MW generation in Turner, GA · In queue since October 2022 · Proposed COD August 2025
110.5 MW
Capacity
1
Components
Solar
3y 5m
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 10m
Schedule
7 months past proposed COD
Construction75%
Queue EntryOct 5, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2025-08-15
Project Details
State
GA
County
Turner
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
North Tifton - Pitts 230 kV Line
Data Source
LBNL