BetaActiveSolarBatterySOCOLBNL
248 MW hybrid in Emanuel, GA · In queue since September 2022 · Proposed COD July 2027
248 MW
Capacity
2
Components
Solar + Battery
3y 6m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 10m
Construction75%
Queue EntrySep 20, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2027-07-01
Technology
Solar124 MW · 50%
Battery124 MW · 50%
Project Details
State
GA
County
Emanuel
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Vidalia - Wadley Primary (Black) 230 kV Line
Data Source
LBNL
No news available for this project.