110.5 MW generation in Treutlen, GA · In queue since September 2022 · Proposed COD August 2026
110.5 MW
Capacity
1
Components
Solar
3y 6m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 11m
Construction75%
Queue EntrySep 9, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-08-15
Project Details
State
GA
County
Treutlen
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Shaddock Creek - Vidalia 115 kV Line
Data Source
LBNL
No news available for this project.