— Project Summary

Queue ID
SOCO-IC-1066
Capacity
80 MW
Technology
Solar
Status
active
Location
Dale, AL
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarSOCOLBNL

80 MW generation in Dale, AL · In queue since September 2022 · Proposed COD August 2030

80 MW

Capacity

1

Components

Solar

3y 6m

In Queue

Suspended

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

7y 11m

In Study38%
Queue EntrySep 9, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-08-15

Project Details

State

AL

County

Dale

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Dothan - Pinckard No. 2 115 kV Line

Data Source

LBNL