BetaActiveSolarBatterySOCOLBNL
160 MW hybrid in Marengo, AL · In queue since September 2022 · Proposed COD April 2027
160 MW
Capacity
2
Components
Solar + Battery
3y 6m
In Queue
Suspended
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 7m
In Study38%
Queue EntrySep 7, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-02
Technology
Solar80 MW · 50%
Battery80 MW · 50%
Project Details
State
AL
County
Marengo
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Bellamy - Demopolis 115 kV Line
Data Source
LBNL
No news available for this project.