— Project Summary

Queue ID
SOCO-IC-1055
Capacity
200 MW
Technology
Solar
Status
active
Location
Coffee, GA
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveSolarSOCOLBNL

200 MW generation in Coffee, GA · In queue since August 2022 · Proposed COD October 2027

200 MW

Capacity

1

Components

Solar

3y 7m

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 2m

Construction75%
Queue EntryAug 26, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-10-01

Project Details

State

GA

County

Coffee

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Douglas - Kettle Creek Primary 230 kV Line

Data Source

LBNL

No news available for this project.