— Project Summary

Queue ID
SOCO-IC-1052
Capacity
80 MW
Technology
Solar+Battery
Status
active
Location
Lee, AL
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarBatterySOCOLBNL

80 MW hybrid in Lee, AL · In queue since August 2022 · Proposed COD June 2026

80 MW

Capacity

1

Components

Solar

3y 7m

In Queue

Suspended

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 10m

In Study38%
Queue EntryAug 26, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-01

Project Details

State

AL

County

Lee

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Martin Dam - Pear Tree SS 115 kV Line

Data Source

LBNL

No news available for this project.