BetaActiveSolarSOCOLBNL
100 MW generation in Coosa, AL · In queue since July 2022 · Proposed COD February 2030
100 MW
Capacity
1
Components
Solar
3y 8m
In Queue
IA Executed
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
7y 7m
Construction75%
Queue EntryJul 18, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2030-02-01
Project Details
State
AL
County
Coosa
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Martin Dam - Sylacauga 115 kV Line
Data Source
LBNL
No news available for this project.