— Project Summary

Queue ID
SOCO-IC-1042
Capacity
200 MW
Technology
Solar+Battery
Status
active
Location
Rockdale, GA
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarBatterySOCOLBNL

200 MW hybrid in Rockdale, GA · In queue since July 2022 · Proposed COD March 2026

200 MW

Capacity

1

Components

Battery

3y 8m

In Queue

Suspended

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 8m

In Study38%
Queue EntryJul 11, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-03-31

Project Details

State

GA

County

Rockdale

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Conyers 115 kV TS

Data Source

LBNL

No news available for this project.