— Project Summary

Queue ID
SOCO-IC-1037
Capacity
150 MW
Technology
Solar
Status
active
Location
Taliaferro, GA
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarSOCOLBNL

150 MW generation in Taliaferro, GA · In queue since May 2022 · Proposed COD April 2026

150 MW

Capacity

1

Components

Solar

3y 10m

In Queue

Suspended

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 11m

In Study38%
Queue EntryMay 19, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-04-13

Project Details

State

GA

County

Taliaferro

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Ray Place Road - Union Point Primary 115 kV Line

Data Source

LBNL

No news available for this project.