— Project Summary

Queue ID
SOCO-IC-1036
Capacity
80 MW
Technology
Solar
Status
active
Location
Montgomery, AL
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarSOCOLBNL

80 MW generation in Montgomery, AL · In queue since May 2022 · Proposed COD January 2027

80 MW

Capacity

1

Components

Solar

3y 10m

In Queue

Suspended

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 8m

In Study38%
Queue EntryMay 19, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-01-15

Project Details

State

AL

County

Montgomery

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Blackbear Solar Farm SS 230 kV Bus

Data Source

LBNL