BetaActiveSolarSOCOLBNL
80 MW generation in Montgomery, AL · In queue since May 2022 · Proposed COD January 2027
80 MW
Capacity
1
Components
Solar
3y 10m
In Queue
Suspended
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 8m
In Study38%
Queue EntryMay 19, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-01-15
Project Details
State
AL
County
Montgomery
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Blackbear Solar Farm SS 230 kV Bus
Data Source
LBNL
No news available for this project.