— Project Summary

Queue ID
SOCO-IC-1035
Capacity
100 MW
Technology
Solar
Status
active
Location
Heard, GA
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarSOCOLBNL

100 MW generation in Heard, GA · In queue since May 2022 · Proposed COD November 2025

100 MW

Capacity

1

Components

Solar

3y 10m

In Queue

Suspended

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 6m

Schedule

4 months past proposed COD

In Study38%
Queue EntryMay 9, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-11-15

Project Details

State

GA

County

Heard

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Dyer Road - East Roanoke 115 kV Line

Data Source

LBNL

No news available for this project.