300 MW hybrid in Jasper, MS · In queue since March 2022 · Proposed COD August 2025
300 MW
Capacity
2
Components
Solar + Battery
4 years
In Queue
Suspended
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 5m
Schedule
7 months past proposed COD
In Study38%
Queue EntryMar 11, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-08-24
Technology
Solar150 MW · 50%
Battery150 MW · 50%
Project Details
State
MS
County
Jasper
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Jasper East SS Substation 230 kV Bus
Data Source
LBNL