BetaActiveSolarBatterySOCOLBNL
300 MW hybrid in Taylor, GA · In queue since February 2022 · Proposed COD June 2024
300 MW
Capacity
2
Components
Solar + Battery
4y 1m
In Queue
IA Executed
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 4m
Schedule
21 months past proposed COD
Construction75%
Queue EntryFeb 25, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2024-06-30
Technology
Solar200 MW · 67%
Battery100 MW · 33%
Project Details
State
GA
County
Taylor
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Patsiliga Creek Substation 230 kV Bus
Data Source
LBNL