— Project Summary

Queue ID
SOCO-IC-1015
Capacity
150 MW
Technology
Solar
Status
active
Location
Mitchell, GA
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarSOCOLBNL

150 MW generation in Mitchell, GA · In queue since January 2022 · Proposed COD September 2027

150 MW

Capacity

1

Components

Solar

4y 2m

In Queue

Suspended

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 8m

In Study38%
Queue EntryJan 28, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-09-30

Project Details

State

GA

County

Mitchell

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

North Tifton - Raccoon Creek 500 kV Line

Data Source

LBNL

No news available for this project.