150 MW generation in Mitchell, GA · In queue since January 2022 · Proposed COD September 2027
150 MW
Capacity
1
Components
Solar
4y 2m
In Queue
Suspended
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 8m
In Study38%
Queue EntryJan 28, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-09-30
Project Details
State
GA
County
Mitchell
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
North Tifton - Raccoon Creek 500 kV Line
Data Source
LBNL
No news available for this project.