— Project Summary

Queue ID
SOCO-IC-1005
Capacity
100 MW
Technology
Solar
Status
active
Location
Burke, GA
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarSOCOLBNL

100 MW generation in Burke, GA · In queue since December 2021 · Proposed COD October 2026

100 MW

Capacity

1

Components

Solar

4y 3m

In Queue

Suspended

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 10m

In Study38%
Queue EntryDec 14, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-10-01

Project Details

State

GA

County

Burke

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Waynesboro Primary - Wilson 230 kV Line

Data Source

LBNL

No news available for this project.