BetaActiveSolarBatterySOCOLBNL
118 MW hybrid in Decatur, GA · In queue since December 2021 · Proposed COD January 2025
118 MW
Capacity
2
Components
Solar + Battery
4y 3m
In Queue
Suspended
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 1m
Schedule
15 months past proposed COD
In Study38%
Queue EntryDec 10, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-01-01
Technology
Solar78 MW · 66%
Battery40 MW · 34%
Project Details
State
GA
County
Decatur
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
East Bainbridge - Spring Creek (Black) 115 kV Line
Data Source
LBNL
No news available for this project.