— Project Summary

Queue ID
SOCO-IC-1001
Capacity
80 MW
Technology
Solar
Status
active
Location
Early, GA
Region
Southeast
Developer
IA Status
Suspended

BetaActiveSolarSOCOLBNL

80 MW generation in Early, GA · In queue since December 2021 · Proposed COD August 2025

80 MW

Capacity

1

Components

Solar

4y 3m

In Queue

Suspended

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 8m

Schedule

7 months past proposed COD

In Study38%
Queue EntryDec 8, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-08-20

Project Details

State

GA

County

Early

Region

Southeast

Developer

Utility

Southern Company

Entity

SOCO

Point of Interconnection

Blakely Primary - Webb 115 kV Line

Data Source

LBNL

No news available for this project.