BetaActiveSolarSOCOLBNL
80 MW generation in Early, GA · In queue since December 2021 · Proposed COD August 2025
80 MW
Capacity
1
Components
Solar
4y 3m
In Queue
Suspended
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 8m
Schedule
7 months past proposed COD
In Study38%
Queue EntryDec 8, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-08-20
Project Details
State
GA
County
Early
Region
Southeast
Developer
—
Utility
Southern Company
Entity
SOCO
Point of Interconnection
Blakely Primary - Webb 115 kV Line
Data Source
LBNL