— Project Summary

Queue ID
SMUD-8
Capacity
344 MW
Technology
Solar+Battery
Status
active
Location
Sacramento, CA
Region
West
Developer
IA Status
Facility Study

BetaActiveSolarBatterySMUDLBNL

344 MW hybrid in Sacramento, CA · In queue since January 2021 · Proposed COD December 2026

344 MW

Capacity

1

Components

Solar

5y 2m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

5y 11m

Facilities Study50%
Queue EntryJan 25, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-15

Project Details

State

CA

County

Sacramento

Region

West

Developer

Utility

Sacramento Municipal Utility District

Entity

SMUD

Point of Interconnection

New substation near Elverta 230kV Substation

Data Source

LBNL

No news available for this project.