BetaActiveSolarBatterySMUDLBNL
250 MW hybrid in Sacramento, CA · In queue since February 2020 · Proposed COD April 2027
250 MW
Capacity
1
Components
Solar
6y 1m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7y 2m
Facilities Study50%
Queue EntryFeb 13, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-01
Project Details
State
CA
County
Sacramento
Region
West
Developer
—
Utility
Sacramento Municipal Utility District
Entity
SMUD
Point of Interconnection
New substation near Cordova 230kV Substation
Data Source
LBNL
No news available for this project.