— Project Summary

Queue ID
SMUD-3
Capacity
250 MW
Technology
Solar+Battery
Status
active
Location
Sacramento, CA
Region
West
Developer
IA Status
Facility Study

BetaActiveSolarBatterySMUDLBNL

250 MW hybrid in Sacramento, CA · In queue since February 2020 · Proposed COD April 2027

250 MW

Capacity

1

Components

Solar

6y 1m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

7y 2m

Facilities Study50%
Queue EntryFeb 13, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-04-01

Project Details

State

CA

County

Sacramento

Region

West

Developer

Utility

Sacramento Municipal Utility District

Entity

SMUD

Point of Interconnection

New substation near Cordova 230kV Substation

Data Source

LBNL

No news available for this project.