BetaActiveSolarBatterySMUDLBNL
550 MW hybrid in Sacramento, CA · In queue since July 2022 · Proposed COD December 2028
550 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 5m
Facilities Study50%
Queue EntryJul 7, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-29
Project Details
State
CA
County
Sacramento
Region
West
Developer
—
Utility
Sacramento Municipal Utility District
Entity
SMUD
Point of Interconnection
New switching station near Rancho Seco 230 kV Substation
Data Source
LBNL
No news available for this project.