— Project Summary

Queue ID
S-C-280
Capacity
29.26 MW
Technology
Solar
Status
active
Location
Fairfield, SC
Region
Southeast
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarS-CLBNL

29.26 MW generation in Fairfield, SC · In queue since June 2024 · Proposed COD December 2025

29.26 MW

Capacity

1

Components

Solar

1y 9m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

1y 6m

Schedule

3 months past proposed COD

In Study38%
Queue EntryJun 5, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

SC

County

Fairfield

Region

Southeast

Developer

Utility

Santee Cooper

Entity

S-C

Data Source

LBNL

No news available for this project.