— Project Summary

Queue ID
S-C-271
Capacity
50 MW
Technology
Solar
Status
active
Location
Chesterfield, SC
Region
Southeast
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarS-CLBNL

50 MW generation in Chesterfield, SC · In queue since June 2024 · Proposed COD June 2028

50 MW

Capacity

1

Components

Solar

1y 9m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4 years

In Study38%
Queue EntryJun 5, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-01