79 MW generation in Allendale, SC · In queue since May 2024 · Proposed COD July 2026
79 MW
Capacity
1
Components
Solar
1y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 2m
In Study38%
Queue EntryMay 15, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-07-01
Project Details
State
SC
County
Allendale
Region
Southeast
Developer
—
Utility
Santee Cooper
Entity
S-C
Data Source
LBNL
No news available for this project.