— Project Summary

Queue ID
S-C-259
Capacity
79 MW
Technology
Solar
Status
active
Location
Allendale, SC
Region
Southeast
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarS-CLBNL

79 MW generation in Allendale, SC · In queue since May 2024 · Proposed COD July 2026

79 MW

Capacity

1

Components

Solar

1y 10m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 2m

In Study38%
Queue EntryMay 15, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-07-01

Project Details

State

SC

County

Allendale

Region

Southeast

Developer

Utility

Santee Cooper

Entity

S-C

Data Source

LBNL

No news available for this project.