BetaActiveSolarS-CLBNL
75 MW generation in Williamsburg, SC · In queue since February 2024 · Proposed COD December 2028
75 MW
Capacity
1
Components
Solar
2y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 10m
In Study38%
Queue EntryFeb 1, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-31
Project Details
State
SC
County
Williamsburg
Region
Southeast
Developer
—
Utility
Santee Cooper
Entity
S-C
Data Source
LBNL
No news available for this project.