BetaActiveSolarS-CLBNL
75 MW generation in Marion, SC · In queue since June 2023 · Proposed COD December 2027
75 MW
Capacity
1
Components
Solar
2y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 6m
In Study38%
Queue EntryJun 1, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
SC
County
Marion
Region
Southeast
Developer
—
Utility
Santee Cooper
Entity
S-C
Data Source
LBNL
No news available for this project.