— Project Summary

Queue ID
S-C-234
Capacity
75 MW
Technology
Battery
Status
active
Location
Hampton, SC
Region
Southeast
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryS-CLBNL

75 MW storage in Hampton, SC · In queue since June 2023 · Proposed COD October 2027

75 MW

Capacity

1

Components

Battery

2y 9m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 4m

In Study38%
Queue EntryJun 1, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-10-31

Project Details

State

SC

County

Hampton

Region

Southeast

Developer

Utility

Santee Cooper

Entity

S-C

Data Source

LBNL

No news available for this project.