— Project Summary

Queue ID
S-C-208
Capacity
74.9 MW
Technology
Solar
Status
active
Location
Aiken, SC
Region
Southeast
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarS-CLBNL

74.9 MW generation in Aiken, SC · In queue since June 2023 · Proposed COD June 2026

74.9 MW

Capacity

1

Components

Solar

2y 9m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3 years

In Study38%
Queue EntryJun 1, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-01

Project Details

State

SC

County

Aiken

Region

Southeast

Developer

Utility

Santee Cooper

Entity

S-C

Data Source

LBNL