BetaActiveGasS-CLBNL
7 MW generation in Anderson, SC · In queue since June 2023
7 MW
Capacity
1
Components
Gas
2y 9m
In Queue
In Progress (unknown study)
IA Status
Interconnection Timeline
Total Duration
2y 9m
In Study38%
Queue EntryJun 1, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
SC
County
Anderson
Region
Southeast
Developer
—
Utility
Santee Cooper
Entity
S-C
Data Source
LBNL
No news available for this project.