BetaActiveSolarS-CLBNL
74.99 MW generation in Darlington, SC · In queue since October 2021 · Proposed COD September 2025
74.99 MW
Capacity
1
Components
Solar
4y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 11m
Schedule
7 months past proposed COD
In Study38%
Queue EntryOct 26, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-09-01
Project Details
State
SC
County
Darlington
Region
Southeast
Developer
—
Utility
Santee Cooper
Entity
S-C
Data Source
LBNL
No news available for this project.