BetaActiveSolarS-CLBNL
75 MW generation in Kershaw, SC · In queue since May 2020 · Proposed COD December 2025
75 MW
Capacity
1
Components
Solar
5y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
5y 7m
Schedule
3 months past proposed COD
In Study38%
Queue EntryMay 8, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-15
Project Details
State
SC
County
Kershaw
Region
Southeast
Developer
—
Utility
Santee Cooper
Entity
S-C
Data Source
LBNL
No news available for this project.