— Project Summary

Queue ID
S-C-109
Capacity
64 MW
Technology
Solar
Status
active
Location
Horry, SC
Region
Southeast
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarS-CLBNL

64 MW generation in Horry, SC · In queue since July 2018 · Proposed COD June 2020

64 MW

Capacity

1

Components

Solar

7y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2020

Interconnection Timeline

Total Duration

1y 11m

Schedule

71 months past proposed COD

In Study38%
Queue EntryJul 6, 2018

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2020-06-01

Project Details

State

SC

County

Horry

Region

Southeast

Developer

Utility

Santee Cooper

Entity

S-C

Data Source

LBNL

No news available for this project.