BetaActiveSolarS-CLBNL
64 MW generation in Horry, SC · In queue since July 2018 · Proposed COD June 2020
64 MW
Capacity
1
Components
Solar
7y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
1y 11m
Schedule
71 months past proposed COD
In Study38%
Queue EntryJul 6, 2018
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2020-06-01
Project Details
State
SC
County
Horry
Region
Southeast
Developer
—
Utility
Santee Cooper
Entity
S-C
Data Source
LBNL
No news available for this project.