BetaSuspendedBatteryPSELBNL
250 MW storage in King, WA · In queue since April 2021 · Proposed COD June 2025
250 MW
Capacity
1
Components
Battery
4y 11m
In Queue
Suspended
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 2m
Suspended38%
Queue EntryApr 15, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-06-01
Project Details
State
WA
County
King
Region
West
Developer
—
Utility
Puget Sound Energy
Entity
PSE
Point of Interconnection
Talbot Hill 230 kV Substation
Data Source
LBNL
No news available for this project.