— Project Summary

Queue ID
PSE-98
Capacity
200 MW
Technology
Battery
Status
active
Location
Pierce, WA
Region
West
Developer
IA Status
IA Executed

BetaActiveBatteryPSELBNL

200 MW storage in Pierce, WA · In queue since March 2021 · Proposed COD December 2023

200 MW

Capacity

1

Components

Battery

5 years

In Queue

IA Executed

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2y 9m

Schedule

28 months past proposed COD

Construction75%
Queue EntryMar 19, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2023-12-15

Project Details

State

WA

County

Pierce

Region

West

Developer

Utility

Puget Sound Energy

Entity

PSE

Point of Interconnection

White River 230kV

Data Source

LBNL

No news available for this project.