BetaActiveWindPSELBNL
750 MW generation in Wheatland, MT · In queue since July 2020 · Proposed COD October 2026
750 MW
Capacity
1
Components
Wind
5y 8m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
6y 3m
Construction75%
Queue EntryJul 31, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-10-31
Project Details
State
MT
County
Wheatland
Region
West
Developer
—
Utility
Puget Sound Energy
Entity
PSE
Point of Interconnection
Proposed New Substation
Data Source
LBNL