— Project Summary

Queue ID
PSE-87
Capacity
100 MW
Technology
Battery
Status
active
Location
Skagit, WA
Region
West
Developer
IA Status
IA Executed

BetaActiveBatteryPSELBNL

100 MW storage in Skagit, WA · In queue since July 2020 · Proposed COD November 2023

100 MW

Capacity

1

Components

Battery

5y 8m

In Queue

IA Executed

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3y 4m

Schedule

28 months past proposed COD

Construction75%
Queue EntryJul 24, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2023-11-30

Project Details

State

WA

County

Skagit

Region

West

Developer

Utility

Puget Sound Energy

Entity

PSE

Point of Interconnection

Fredonia 115-kV Substation

Data Source

LBNL

No news available for this project.